California ISO · Resource Interconnection Standards

Cluster 16 interconnection requests

Loading the preliminary queue.

Independent project built from the California ISO public queue report. Not affiliated with or endorsed by the California ISO. The list is preliminary: requests still in completeness review may be added, and scoring during the Customer Engagement Window decides which projects enter the cluster study.

Oct 1 to 15, 2026Application window
Oct 16, 2026Preliminary queue posted
Oct 16, 2026 to Jan 13, 2027Customer Engagement Window and scoring
Jan 14, 2027Cluster study begins

What was requested

Net MW at the point of interconnection, by project technology

Where the projects sit

Circle area shows MW requested per county

By study area

Net MW at POI, split by technology

By transmission owner

Net MW at POI

Requested commercial operation

GW by requested COD year

Submissions by day

Requests by application date within the window

Busiest points of interconnection

Top 12 POIs by MW requested, with request count

Interconnection voltage

Net MW at POI by voltage level

Project size

Number of requests by net MW at POI

Against Cluster 15

Cluster 16 as submitted, next to Cluster 15 as listed in the ISO report posted July 16, 2026. Not affected by the filters above.

The Cluster 15 figures are the projects in that report's active and withdrawn sheets, after the ISO's intake screening, so this compares a raw intake with a screened one.

All requests